Bid Opening Date: September 22, 2009
Estimate $ 155,000 - $165,000
These results are unofficial until reviewed by the engineer.
Bids were submitted by:
Contrator | Bid Amount |
Ritenour & Sons Const. Co., Inc. | $ 66,000.00 |
Ford General Industries | $ 119,000.00 |
Speria Construction, Inc. | $ 127,000.00 |
A.W. McNabb, LLC | $ 129,000.00 |
Dore & Associates Contracting | $ 169,000.00 |
Infinity Crane & Excavation | $ 198,900.00 |
Kaclik Builders LLC | $ 214,056.00 |
Elisha Industries | $ 228,350.00 |
Joseph B. Fay Company | $ 231,000.00 |
Brayman Construction | $ 257,998.00 |
Advanced Builders, Inc. | $ 332,500.00 |
Neumeyer Environmental Services | $ 425,000.00 |