Etna - Greeley Avenue Bridge Rehabilitation - CD 31 3.10.5
Etna Borough
Greeley Avenue Bridge Rehabilitation
Bid Opening Date: December 14, 2018
Estimate $ 260,000 +/-
Brief description of project. The rehabilitation of the existing bridge along Leonard Avenue at the intersection with Mary Lue Drive over Little Pine Creek. The work includes removal of existing bridge pre-stressed concrete beams, deck, and wearing surface to limits shown on the plans, and installation of new pre-stressed hollow planks and topping slab. Work also includes installation of new guide rails, a parapet wall, and various concrete repairs to abutments.
Bids received by:
Contractor | Base Bid #1 | Base Bid #2 |
Gary Metzinger Cement Contractors, Inc. | $250,040.00 | $236,989.60 |
Beech Construction, Inc. | No Bid | No Bid |
ConstructConnect (Reporting Agency) | No Bid | No Bid |
A. Merante Contracting | $283,650.00 | No Bid |
Bill Anskis Company, Inc. | No Bid | No Bid |
Allison Park Contractors, Inc. | $390,000.00 | $380,000.00 |
Advantage Steel Construction, LLC | No Bid | No Bid |
Builders Exchange, Inc. (Reporting Agency) | No Bid | No Bid |
Gregori Construction, Inc. | $235,850.00 | $224,850.00 |
Bioni Drilling, Inc. | No Bid | No Bid |