Sharpsburg Borough - Catch Basin / Storm Inlet Reconstruction CD 46 3.12.12

Sharpsburg Borough
Catch Basin / Storm Inlet Reconstruction - CD 46 3.12.12
Bid Opening Date:  August 28, 2020
Estimate $55,000 +/-

 

Brief description of project:  Remove and install new catch basins at twelve locations in the borough.

Bid Packages were requested by:

Contractor Bid Amount
John D. Caruso, Inc. No Bid 
Protocol LLC  $52,611.00 
U&S Construction  $79,200.00 
Valley Brook Services LLC  No Bid
M. O'Herron Company $80,00.00 
Baiano Construction Inc. $71,851.40 
Satira Construction Inc. No Bid
Jet Jack, Inc. $102,500.00 
ConstructConnect (reporting agency) No Bid
A. Folino Construction Inc. $70,700.00 
Osiris Enterprises No Bid


Follow up Questions
. Please review the FAQs and your bid package before submitting any questions. Technical questions regarding the bid package may be submitted to the project engineer:  Shane Michael, Senate Engineering, 412-826-5454.