Reserve - Spring Garden Stream Improvements Ph. III - CD 46 7.3 F
Reserve Township
Spring Garden Stream Improvements Ph. III - CD 46 7.3 F
Bid Opening Date: October 23, 2020
Estimate $55,000 +/-
Brief description of project. Project includes bank stabilization along with geotextiles, excavation, rip-rap, erosion control blanket, live cuttings, bypass pumping, grading and seeding.
Bid Packages were requested by:
Contractor | Bid Amount |
Builder's Exchange (reporting agency) | No Bid |
Protocol, LLC | No Bid |
C. Crump, Inc. | $53.000.00 |
ConstructConnect (reporting agency) | No Bid |
Meadville Land Service, Inc. | No Bid |
Jet Jack, Inc. | $59,850.00 |
S.E.T., Inc. | $124,338.00 |
Penn Landscape & Cement Work | No Bid |
Osiris Enterprises | No Bid |
Follow up Questions. Please review the FAQs and your bid package before submitting any questions. Technical questions regarding the bid package may be submitted to the project engineer Phil Herman, Senate Engineering (412-826-5454).